If you need to periodically calculate dates on your AS/400 relative to a given date to determine reporting limits such as month end, month begin, this tip contains a helpful service program.

We received this tip regarding data calculations on the AS/400 that Kevin Ketzler thought would be helpful to System...

i users. If you have a tip, please send it to our editor's inbox.

As a consultant, over the course of many projects at different places, I periodically would have to calculate certain dates relative to a given date to determine reporting limits (e.g., month end, month begin). I also often had to determine the day of the week. So, I put together a little text file that first contained the calculations for these values. I have since converted the text file to contain procedures so that I can easily create a service program to perform the various date calculations.

 

 

h nomain option(*nodebugio:*srcstmt)


d getPriorMonthEnd...
d pr d
d pDate d const

d getPriorMonthBegin...
d pr d
d pDate d const

d getMonthBegin pr d
d pDate d const

d getMonthEnd pr d
d pDate d const

d getDayOfWeek pr 1p 0 Mon = 0 ... Sun = 6
d pDate d const

d isWeekDay pr n
d pDate d const

d isWeekEnd pr n
d pDate d const

p getPriorMonthEnd...
p b export
d getPriorMonthEnd...
d pi d
d pDate d const
/free
return pDate - %days(%subdt(pDate:*days));
/end-free
p getPriorMonthEnd...
p e

p getPriorMonthBegin...
p b export
d getPriorMonthBegin...
d pi d
d pDate d const
/free
return getMonthBegin(pDate - %months(1));
/end-free
p getPriorMonthBegin...
p e

p getMonthBegin b export
d getMonthBegin pi d
d pDate d const
/free
return getPriorMonthEnd(pDate) + %days(1);
/end-free
p getMonthBegin e

p getMonthEnd b export
d getMonthEnd pi d
d pDate d const
/free
return getPriorMonthEnd(pDate + %months(1));
/end-free
p getMonthEnd e

p getDayOfWeek b export
d getDayOfWeek pi 1p 0 Mon = 0 ... Sun = 6
d pDate d const
/free
return %rem(%diff(pDate:d'0001-01-01':*days):7);
/end-free
p getDayOfWeek e

p isWeekDay b export
d isWeekDay pi n
d pDate d const
/free
return getDayOfWeek(pDate) < 5;
/end-free
p isWeekDay e

p isWeekEnd b export
d isWeekEnd pi n
d pDate d const
/free
return getDayOfWeek(pDate) > 4;
/end-free
p isWeekEnd e

ABOUT THE AUTHOR: Kevin C. Ketzler is a designer, analyst, and project lead for IBM Solutions Practice at Affiliated.
 

This was last published in July 2008

Start the conversation

Send me notifications when other members comment.

By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Please create a username to comment.

-ADS BY GOOGLE

SearchDataCenter

Close